Procedures for Baghdad liquid gas shipment completed, says Felah Mewlûd

2 min read
Procedures for Baghdad liquid gas shipment completed, says Felah Mewlûd

What happened?

Felah Seyîd Mewlûd, director general of oil and minerals at the Kurdistan Region's Ministry of Natural Resources, announced that all administrative procedures for the household liquefied gas due to arrive from Baghdad have been completed. According to Mewlûd, transport preparations carried out with companies have also been finalised. The shipment now awaits Baghdad's decision.

On Monday, 23 November 2026, Mewlûd said they were in constant contact with officials of the Iraqi Ministry of Oil: “We are in contact with officials of the Iraqi Ministry of Oil every day on this matter. The Iraqi oil minister is expected to clarify today when the gas will be sent. If he instructs his subordinate units to send the gas, loading will begin immediately and the gas will be dispatched to the Kurdistan Region.” According to Mewlûd, the gas will be transported in several convoys.

Mewlûd stated that the delay was caused by the Iraqi Ministry of Oil. Iraqi Prime Minister Ali al-Zaidi decided to send the gas about two weeks ago.

According to information provided by Mewlûd, the Kurdistan Region requested a total of 760 tonnes of gas for four provinces: 300 tonnes for , 260 tonnes for and , and 200 tonnes for . Mewlûd said Baghdad may review this amount in line with its own stocks: “Whatever amount comes is good, we have no problem, because we have stocks stored at the directorates. But the more there is, the better.”

As an example, Mewlûd described a scenario in which only 500 tonnes arrive. In that case, Hewlêr would receive about 200 tonnes, Silêmanî 180 tonnes and Dihok 120 tonnes.

On the Kormor gas field, Mewlûd said: “According to the information I have received, production at Kormor will not resume for another week, because the repairs still need time.” According to Mewlûd, stocks in the region's depots are sufficient until the field resumes operation or gas arrives from Baghdad.

The Kormor field, in the Qadirkerem subdistrict of Çemçemal district in Silêmanî province, was targeted by a drone attack on the night of 8 November 2026. Production stopped after the attack. Electricity generation also fell by between 2,500 and 2,800 megawatts. The following day, at the request of the Kurdistan Region's Ministry of Natural Resources, Ali al-Zaidi tasked the Iraqi Ministry of Oil with supplying the necessary gas.

Gas production at Kormor began in October 2008. The Emirati company Dana Gas is investing in the field. The field supplies 67 percent of the region's electricity, and it is also the main source for household gas plants.