14-kilometre left lane of Hêzop-Dukan road completed

2 min read
14-kilometre left lane of Hêzop-Dukan road completed

What happened?

A new 14-kilometre section of the dual carriageway project between Hêzop and Dukan, in province, opens to traffic on Tuesday, 3 November 2026. The contractor has fully completed asphalting and improvement work on this stretch.

The new section runs between the village of Kanî Wutman and the area around Xelekan subdistrict. Only the left lane has been completed so far. An earlier 11-kilometre section of the project opened with both lanes on 23 July 2026. That section was built to the highest international motorway standards.

The old road was rough, narrow and full of potholes, which caused many fatal traffic accidents in past years. The accidents occurred mainly near Kanî Wutman, Hêzop and Xelekan. The route links the city of Silêmanî with Ranya district and the Raperîn Independent Administration.

Project manager and engineer Muhammed Ahmed said: "After this section opens, asphalt paving will be temporarily suspended for this year because of the onset of winter and the rains, but the company's staff will continue maintenance and improvement tasks on the remaining parts of the road."

According to Ahmed, construction of a large 380-metre dual carriageway bridge on the route is ongoing. Each direction of the bridge will be 15 metres wide. Ahmed said it will be one of the longest bridges built on dual carriageways in Silêmanî province.

The project has a total length of 38 kilometres. The remaining stage between Xelekan and Dukan is the most difficult part in engineering terms: the mountainous terrain and numerous bends require extensive excavation in rock. A period of 1000 days, until May 2028, has been set for this stage, while engineering teams are trying to deliver the work ahead of schedule.

The project was first launched in 2012-2013 and was halted for many years because of the financial crisis that hit the region. The ninth cabinet of the Kurdistan Regional Government restarted the work and awarded the contract to Garden Group.