Silêmanî got 4 to 5 hours of power in 24 hours, electricity director says

2 min read
Silêmanî got 4 to 5 hours of power in 24 hours, electricity director says

What happened?

Enwer Heme Seîd, director general of electricity for province in the Kurdistan Region, said an attack on the Kormor gas field had reduced electricity production. According to Heme Seîd, only 4 to 5 hours of electricity could be supplied over the past 24 hours within the boundaries of Silêmanî, and the Raperîn Administration. In a statement on Tuesday, 10 November 2026, Heme Seîd said gas production at Kormor had fallen to zero. He said output at gas-fired power plants had also stopped completely and that they were trying to share out the available electricity fairly. "In this extraordinary situation we cannot draw up a schedule for electricity distribution," he said.

The Kormor gas field, in the Çemçemal district of Silêmanî province, was hit by a drone attack on the night of Sunday, 8 November 2026. Gas deliveries to the power plants were cut off after the attack. National grid output reportedly dropped by more than 2,500 megawatts. The Silêmanî, Bazyan, and power plants went out of service.

According to information provided by Heme Seîd, two of the region's six electricity directorates are covered by the Rûnakî Project. Before the attack, the project areas received 24 hours of electricity a day and other areas 15 hours. Heme Seîd said demand at that time was between 650 and 900 megawatts.

According to Heme Seîd, three units are running at Dukan Dam and one unit at Derbendîxan Dam. The 51-megawatt plant in Taslûce, the 29-megawatt plant in Silêmanî and the Agrico plant in Germiyan are also still producing. In Hewlêr the Xurmele and Xebat plants are operating, and in Dihok the Baedrê plant. Heme Seîd said these plants run on fuel oil and are working at full capacity.

Heme Seîd recalled that Kormor's two gas storage facilities had been destroyed in earlier attacks. He said that even if such a facility existed anywhere in the world, it could hold enough gas for 40 to 50 hours of power plant operation. As far as he knew, he said, the power plants have no such storage facilities. In his view, the source of the problem is not the Ministry of Electricity or the generating companies but the lack of fuel and gas. Heme Seîd said distribution would also improve once gas production at Kormor returns to normal.